A. Activity E is a logical dangle in relation to the sink before the finish milestone.
B. Activity F is a logical dangle in relation to the burst point after the start milestone.
C. You can not calculate a critical path when lags and/or leads are calculated in percent.
D. Activities E to F need another task drawn as a hammock to calculate Level Of Effort.
answer => A