A. For the better only, a positive effect.
B. For the worse, a negative effect.
C. Both better or worse, a positive or negative effect.
D. Neither better nor worse, neither a positive nor a negative effect.
Answer => C
A. For the better only, a positive effect.
B. For the worse, a negative effect.
C. Both better or worse, a positive or negative effect.
D. Neither better nor worse, neither a positive nor a negative effect.
Answer => C
A. Project team members
B. Project sponsor
C. Individuals responsible for risk management policies and templates
D. Key stakeholders
answer => B
A. An information-gathering technique where experts perform a Strengths, Weaknesses, Opportunities, Threats (SWOT) analysis.
B. An information-gathering technique where experts are briefed about the project and then interviewed for their opinions.
C. An information-gathering technique where experts meet and generate ideas about project risk.
D. An information-gathering technique where experts participate anonymously and ideas about project risk are gathered via a circulated questionnaire.
answer => D
A. Mitigation
B. Deflection
C. Avoidance
D. Transfer
answer => C
A. Developing a plan to minimize potential impact
B. Creating contingency reserves in money and time
C. Making additional resources available
D. Developing a plan to minimize probability
answer => B
A. Just before any major meeting with the client
B. On a regular basis throughout the project
C. Only when justified by the awareness of new risks becoming a possibility
D. When preparing the project plan
answer => B
A. A deterministic scheduling method.
B. A probabilistic scheduling simulation method.
C. A probabilistic cost management technique.
D. A risk identification technique.
answer => B

A. Option A
B. Option B
C. Option C
D. Option D
answer => D
A. Uncertainty and risk are greatest at the start of the project and lowest at the end.
B. The amount at stake is lowest at the end of the project and greatest at the start.
C. Analysis of risks using probability and consequences helps identify those risks that should be managed aggressively.
D. Opportunities are positive outcomes of risk.
answer => B
A. p = .4
B. p = .003
C. p = .014
D. Probability cannot be determined from the data given

answer => B