A. 164 - 173 days
B. 144 - 194 days
C. 119 - 219 days
D. 159 - 179 days
answer => D
A. 164 - 173 days
B. 144 - 194 days
C. 119 - 219 days
D. 159 - 179 days
answer => D

A. Activity E is a logical dangle in relation to the sink before the finish milestone.
B. Activity F is a logical dangle in relation to the burst point after the start milestone.
C. You can not calculate a critical path when lags and/or leads are calculated in percent.
D. Activities E to F need another task drawn as a hammock to calculate Level Of Effort.
answer => A
A. Initiating
B. Executing
C. Planning
D. Controlling
answer => C

What is the expected value of the number of days to complete the Project?
A. 47.3
B. 22.0
C. 32.3
D. 48
answer => C
-
Activity B Early Start is Day 1; Early Finish is Day 3.
Late Start is Day 6; Late Finish is Day 8.
Activity B has a FS relationship with succeeding Activity C. Activity B has no other immediate succeeding activities. Activity C has an Early Start of 6 days and a Late Start f 11 days.
What is the float or total float for Activity B? (use PMBOK Guide definition of “float” as defined above.)
A. 2 days
B. 5 days
C. 7 days
D. 0 days
answer => B
What is the free float for Activity B? (use definition of “free float” as defined in PMBOK guide above.)
A. 2 days
B. 5 days
C. 7 days
D. 0 days
answer => A
A. AOA
B. AON
C. ADM
D. GERT
answer => B
A. FS
B. FF
C. SS
D. SF
answer => D
A. Lead
B. Lag
C. Slack
D. a or b
answer => A
A. A milestone
B. A hammock
C. A dummy activity
D. A hanger
answer => C