YOUPMP :: PMP EXAM PREP FOR EVERYONE

  • The first project is a process optimization which would result in a cost reduction of $120,000 per year.This benefit would be achieved immediately after the end of the project.
  • The second project would be the development of a new product which could produce the following net profits after the end of the project:

    1 year: $ 15,000
    2 year: $ 125,000
    3 year: $ 220,00

    Assumed is a discount rate of 5 % per year.Looking at the present values of these projects’ revenues in the first 3 years, what is true?

A. Both projects are equally attractive.
B. The first project is more attractive by app.7%.
C. The second project is more attractive by app.5%.
D. The first project is more attractive by app.3%.

answer => D

  1. The first project is a process optimization which would result in a cost reduction of $120,000 per year. This benefit would be achieved immediately after the end of the project.
  2. The second project would be the development of a new product which could produce the following net profits after the end of the project:
1. year: $ 15,000
2. year: $ 125,000
3. year: $ 220,000

Assumed is a discount rate of 5% per year. Looking at the present values of these projects’ benefits in the first 3 years, what is true?

A. Both projects are equally attractive.
B. The first project is more attractive by app. 7%.
C. The second project is more attractive by app. 5%.
D. The first project is more attractive by app. 3%.

answer => D

A. Present Value = Future Value/(1+R)
B. Present Value = Future Value/(1-R)
C. Present Value = (1+R)
D. Present Value = (1-R)n / Future Value

answer => A

A. You are only progressing at 86% of the rate originally planned
B. You are progressing at 125% of the rate originally planned
C. You are progressing at 116% of the rate originally planned
D. You are only progressing at 80% of the rate originally planned

answer => D

A. NPV
B. Benefit cost ratio
C. Payback period
D. Law of diminishing returns

answer => D

A. 227.3
B. 250
C. 274.7
D. 525

answer => C

A. The EAC is a positive number, which means the project will finish under budget.
B. You do not have enough information to calculate CPI.
C. The CV is a negative number in this case, which means you’ve spent less than you planned to spend as of the measurement date.
D. The CV is a positive number in this case, which means you’re under budget as of the measurement date.

answer => D

A. 100,000 units
B. Three years
C. Five years
D. 25,000 units

answer => D

A.  $25,000
B. $20,000
C. $22,000
D. $24,000

answer => C

A. 1.25
B. .66
C. .80
D. 1.33

answer => D



Search


Google

Proudly powered by WordPress.
Copyright © YOUPMP :: PMP EXAM PREP FOR EVERYONE All rights reserved.