A. Proposals.
B. Evaluation criteria.
C. Contract negotiation.
D. Contract.

answer => D

A. You document the poor performance in written form and send the correspondence to the subcontractor.
B. You terminate the contract for poor performance and submit a change request through Contract Administration.
C. You submit a change request through Contract Administration demanding that the subcontractor comply with the terms of the contract.
D. You agree

answer => C

A. Evaluation criteria
B. Organizational policies
C. Procurement documents
D. a and b

answer => D

A. Can often be found in procurement documents
B. Can be objective or subjective
C. May be limited to purchase price if procurement item is readily available from number f sources
D. all of the above

answer => D

A. Procurement documents are used to solicit proposals from prospective sellers.
B. Invitation for Bid and Request for Proposal are two examples of procurement documents.
C. Procurement documents should be structured to facilitate accurate and complete responses from prospective sellers.
D. All of the above

answer => D

A. Procurement Planning
B. Solicitation
C. Solicitation Planning
D. Source Selection

answer =>  B

A. Procurement planning should include consideration of potential subcontracts
B. Procurement planning does not include consideration of potential subcontracts since this is the duty of the contractor.
C. Subcontractors are first considered during the Solicitation Process
D. None of the above

answer => A

A. Whether to procure
B. How to procure and how much to procure
C. What and when to procure
D. All of the above

answer => D

A. Weighting system
B. Screening system
C. Selecting system
D. All of the above

answer => A

A. A cost reimbursable contract
B. A lump sum contract
C. A unit price contract
D. A fixed price contract

answer => C