A. Differences between or among stakeholders should be resolved in favor of the customer.
B. Managing stakeholder expectations may be difficult because stakeholders often have very different objectives, that may come into conflict.
C. Project stakeholders may influence the course of the project and its results.
D. Differences between or among stakeholders should be resolved in the most cost efficient manner consistent with project objectives.

answer => D

One Response to “All of the following statements concerning project stakeholders are true except”

  1. Renee

    d